Carol’s Home Construction Update

Author: melissa  |  Category: Time Frame Updates
  1. American Roofing Concepts is back on the roof today and is expected to finish the roof today or tomorrow at the latest.
  2. Jordy will be on-site with the electrician (EDC) tomorrow (Friday).
  3. HVAC has been completed by Andersen Heating and Cooling.
  4. Stairs to Frog– I am waiting on a call back from Southern Staircase to see if they have measured.
  5. Garage DoorLeon at Southeastern Garage Doors will go by the house this week and let us know about a delivery/installation date.
  6. Sheetrock – LowCountry Drywall has measured and is ready to install the week of September 22nd.
  7. G&S/James Hardie – G&S should be measuring this week and will soon after place an order with James Hardie.
  8. Kitchen Cabinets – Welcom has gone ahead and placed the order. The cabinets should be here in a couple weeks.
  9. Granite –  MVP has decided to upgrade us from Benissimo squares to 3cm granite slabs.

Thank you to everyone who is so graciously donating time, money and services to help Carol regain some of the freedoms that were taken from her. This is a life changing project for the Armstrongs. Make sure you check out the webcam by clicking here: http://carolshome.info/?page_id=4

Melissa